Plenty to See Here

It has been a while since our last post and there is so much to mention, but first here's a picture of the High School!

 It's fitting that the first layer of "skin" be black and purple.

It's fitting that the first layer of "skin" be black and purple.

The third floor has been poured, the HVAC ducting for floor one is now in place, the studs for all the walls on floor one are also in place, and the main stairs to the second floor are ready.

 HVAC!

HVAC!

 Pouring the deck for Floor 2.

Pouring the deck for Floor 2.

 Looking Good

Looking Good


The field is currently under construction. It's unsettling to see it this way, but we all know the end result will be amazing; and since there will no longer be a need for the grass to recover, it will allow more use during the school year.

 Ready for a new field!

Ready for a new field!


Finally, here are some key dates for the construction process.

6-16-18 DOT Road Construction thru 7-23-18
6-22-18 Multi-Purpose Room Slab Pour
7-20-18 Masonry thru 9-13-18
6-15-18 HS Parking & Landscaping thru 8-21-18
10-9-18 Punch Out thru 10-16-18
10-17-18 Final Inspections thru 10-23-18
10-24-18 Certificate of Occupancy

Stay Tuned for more developments and pictures!